You’ve finally decided to remodel your entire house, and a dozen new questions are crowding in. Chief among them: How long does a whole-home remodel take? Not knowing the answer makes it hard to plan anything else.
Koze Design & Build, led by Jason Craig, has spent two decades guiding Lower Mainland homeowners through full-home remodels in Pitt Meadows. This breakdown lays out real timeframes for your project.

Breaking Down the Whole-Home Remodelling Timeline
A typical home remodelling timeline runs seven to 12 months, from planning through move-in. Knowing how long a whole-home remodel takes helps you plan around the work instead of guessing.
Design and Planning
Architectural planning begins with drawings and interior material selections. Structural engineering and municipal permit processing follow before construction. This phase typically takes three to five months.
The Construction Phase
Once the construction phase begins, demolition and structural framing come first. Plumbing and electrical rough-ins follow, along with HVAC rough-ins. Insulation and drywall complete the stage, which typically lasts four to seven months.
Finishes and Handover
The final one to two months cover millwork and custom cabinetry, followed by flooring and fixture installation. Fine trim leads into final inspections and final walkthrough quality checks.
Factors That Affect How Long Your Remodel Will Take
Not every renovation moves at the same pace. A full-home remodel touching every room takes longer than updating one space.
A few changes tend to extend that schedule most:
- Load-bearing walls: Moving one of these requires engineering review and sign-off.
- Added square footage: Expanding your footprint means more foundation work.
- Layout reconfigurations: Rerouting plumbing or wiring extends the rough-in stage.
Any one of these can push your project past a standard schedule.
Permits and Materials Can Slow Down Your Schedule
Permit review times vary across the Lower Mainland. Submitting complete drawings the first time avoids delays before construction starts.
Material delays cause just as many slowdowns as paperwork. Choosing durable, in-stock finishes early helps you avoid backorders. Vetting your contractor matters, too, and this resource on hiring construction and remodelling services you can trust helps you spot red flags.
The Koze Approach to a Predictable Remodelling Project
Koze Design & Build has structured its process to remove the guesswork from scheduling. Every remodelling project is treated as one coordinated build.
Three commitments help keep every schedule on track:
- One coordinated team: A single contact manages design through construction.
- Fixed-price contracts: Costs and selections are locked in before construction starts.
- Ongoing project updates: You get regular progress reports at every stage.
This structure lets Koze give homeowners a schedule they can trust.
Your Whole-Home Remodel Starts With Koze Design & Build
We’ve found predictable schedules come down to the certainty you build in before the first hammer swings. Those who feel confident about their timeline treat planning as seriously as the build itself.
Our guide on preparing for a whole-home remodel covers what to gather before we meet. If you’re weighing how long a whole-home remodel will take in Pitt Meadows or the Lower Mainland, call Koze Design & Build today at (604) 315-7095 to schedule a consultation and map out your project schedule.